What type of rapid transit system was put in place exactly?
I to am wondering what this new poster is talking about exactly?
Phase 2 of the Southwest BRT line will be open in April. Until now, only Phase 1 was complete, which included the dedicated corridor running from Main @ Stradbrook and merged with the Jubilee overpass to continue its route to U of M down Pembina, as well as the giant bus loop they built right at IGF to accommodate transit and PnR buses to the stadium (and obviously student and employee transport to the university). Phase 2 extends the BRT corridor along the west side of Pembina and goes all the way to the campus/stadium, bypassing just about all the traffic on Pembina and Osborne Village.
I use this route to work from time to time and the only part that sucks is the part you have to venture on that isn't complete...so I expect that when it is done it will be an enormous improvement not only for those using it but for everyone else too as it will take many buses off the main routes.